JUN 2021
24 JUN 2021
Beautiful day in Portland. Drywall installation going on at Building 4,
while the insulation is being installed at Building 5.
18 JUN 2021
Inside Building 3, drywall, everywhere. And the happy news comes in. 50% of the work is done for this building!
18 JUN 2021
Sewer line digging is in progress at the front of Building 1.
15 JUN 2021
The accent siding walls are showing up at the Exterior of Building 3, where cladding is taking place.
9 JUN 2021
2nd floor patio sliding door has been installed at Building 3, which is leading the whole project. In the same building, we are working on exterior siding and insulation as well.
9 JUN 2021
2nd floor framing and roof trusses continues at Building 6. In the same building is the community tech center, which will be the core of the HOMMA Intranet of this project. Secondly, we are currently preparing to dig the sewer line. Lastly, the south elevation photo shows no sign of GreenHammer office anymore, meaning we will soon be starting our last building of the whole project, which will be Building 2!
8 JUN 2021
Roof trusses are going on at Building 6.
3 JUN 2021
At Building 1, MEP rough in is taking place. Starting on the 2nd floor wood framing at Building 6. The third picture shows North Elevation, which shows from the left, Building 6, 5, and 4. Last picture shows West Elevation, Building 3 and 4.
3 JUN 2021
This will be the Cedar we will be using for the accent siding wall.