MAY 2021
28 MAY 2021
Framing at Building 6 (the corner building with basement storage) continues. The basement storage is starting to show its presence.
28 MAY 2021
Walk down the stairs, open the newly installed door and you will be outside. Outside at Building 3, the door siding is taking place which takes preciseness and accuracy.
21 MAY 2021
Doors are being installed at Building 3. Building 6 continues its progress with the wall framing, and you can see what the elevator pit looks like from the 2nd floor. And we would like to introduce our General Contractor (right) and the electrician (left) who are working very hard with us to make this HOMMA HAUS happen.
19 MAY 2021
At Building 3, downlights in the patio are being installed.
14 MAY 2021
HOMMA signage can now be seen at the site!
14 MAY 2021
A beautiful natural sunlight is coming in through the sliding doors/windows at the corner unit of Building 3. 1st floor (kitchen, dining and living room) and 2nd floor bedroom.
14 MAY 2021
Framing at Building 6 (the corner building with basement storage and bike storage) is rapidly progressing with skilled contractors.
4 MAY 2021
Patio sliders that allow easy access to the outdoors from the living room are installed at Building 3, leading the whole project. West elevation framing at Building 1 and start of the framing at Building 6 is taking place.