APR 2021
28 APR 2021
The first photo is the view from the southside facing north, where the main entrance will be located. The second photo is the view from Building 5 that faces south, courtyard and the main entrance.
28 APR 2021
Working under the clear blue sky at Building 1. The white panel is placed in the walls of the units at Building 3, that will house the electrical transformers that power all of the LED lights and sensors. Lastly, another beautiful view to enjoy from the corner unit of Building 4.
27 APR 2021
Completed the elevated concrete slab which will become the front patio for the two units at Building 6. The lower level will be the separate bike storage for all the units.
26 APR 2021
MEP (mechanical, electrical & plumbing) rough in continues in Building 3, 4, and 5.
23 APR 2021
2nd floor wall framing continues at Building 1, getting covered with plywood ready for roofing.
22 APR 2021
4 units will be in Building 3 and 3 units in Building 4.
MEP (mechanical, electrical & plumbing) rough in is taking place in these buildings.
20 APR 2021
Our townhome community is increasing its presence in the neighborhood, little by little but surely.
15 APR 2021
2nd floor framing started at Building 1. Exterior weather barriers are being installed for Building 3, 4 and 5. Elevated slab forming continues at Building 6. (You can compare the photo from the same angle taken on March 31).
13 APR 2021
Sunny days continue in Portland, and so is the wall framing at Building 1. Loading drywall into Building 3. Framing completed at Building 5 and you can see the progress by comparing the photo from the same angle taken on 16 MAR! Elevated slab forming and rebar is taking place at Building 6 (where the bike storage will be) .
2 APR 2021
Another sunny day. Wall framing is rapidly going on at Building 1 and Building 5 roof trusses are going on and getting covered with plywood ready for roofing.